Project Timeline Builder

Pick a project type and size to see a typical phased timeline — directionally useful, not a fixed contract schedule.

Typical phased schedule — actual durations vary by scope and trades.

Planning & ordering14 days
Day 114
Strip-out3 days
Day 1517
First fix (services)5 days
Day 1822
Build & surfaces10 days
Day 2332
Second fix & snagging4 days
Day 3336
How this is calculated

Each phase uses a base day count scaled by project size (small ×0.75, medium ×1, large ×1.35).

Add buffer for public holidays, curing times (plaster, waterproofing), and snagging.

Related reading

Indicative durations only. Weather, material lead times, and trade availability will shift real dates.